			U.S.
			Department of Transportation 
		 | 
		
			Federal
			Transit Administration 
		 | 
	
Quarter
3 (Apr - Jun), FY 2019 Milestone Progress Report
	
	
	
		
			Federal Award Identification Number
			(FAIN) 
		 | 
		
			PA-2019-021-00 
		 | 
	
	
		
			Temporary Application Number 
		 | 
		
			1947-2019-5 
		 | 
	
	
		
			Award Name 
		 | 
		
			FY 2019 Section 5337 - SEPTA SOGR
			Projects 
		 | 
	
	
		
			Award Status 
		 | 
		
			Active (Executed) 
		 | 
	
	
		
			Award Budget Number 
		 | 
		
			0 
		 | 
	
Part
1: Recipient Information
	
	
		
			Name:
			Southeastern Pennsylvania Transportation Authority 
		 | 
	
	
		
			
				
				
				
				
				
					
						Recipient ID 
					 | 
					
						Recipient OST Type 
					 | 
					
						Recipient Alias 
					 | 
					
						Recipient DUNS 
					 | 
				 
				
					
						1947 
					 | 
					
						Transit Authority 
					 | 
					
						SOUTHEASTERN PENNSYLVANIA
						TRANSPORTATION AUTHORITY 
					 | 
					
						044543841 
					 | 
				 
			 
			 
			 
		 | 
	
Part
2: Award Information
	
	
		
			Title:
			FY 2019 Section 5337 - SEPTA SOGR Projects 
		 | 
	
	
		
			
				
				
				
				
				
				
				
					
						FAIN 
					 | 
					
						Award Status 
					 | 
					
						Award Type 
					 | 
					
						Date Created 
					 | 
					
						Last Updated Date 
					 | 
					
						From TEAM? 
					 | 
				 
				
					
						PA-2019-021-00 
					 | 
					
						Active (Executed) 
					 | 
					
						Grant 
					 | 
					
						2/21/2019 
					 | 
					
						8/28/2019 
					 | 
					
						No 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
	
	
	
		
			
				Funding Source 
			 | 
			
				Section of Statute 
			 | 
			
				CFDA Number 
			 | 
			
				Amount 
			 | 
		
	
	
		
			
				5337 - State of Good Repair Grants 
			 | 
			
				5337 
			 | 
			
				20525 
			 | 
			
				$131,379,803 
			 | 
		
		
			
				Local 
			 | 
			
				 
				 
			 | 
			
				 
				 
			 | 
			
				$9,817,388 
			 | 
		
		
			
				Local/In-Kind 
			 | 
			
				 
				 
			 | 
			
				 
				 
			 | 
			
				$0 
			 | 
		
		
			
				State 
			 | 
			
				 
				 
			 | 
			
				 
				 
			 | 
			
				$23,027,564 
			 | 
		
		
			
				State/In-Kind 
			 | 
			
				 
				 
			 | 
			
				 
				 
			 | 
			
				$0 
			 | 
		
		
			
				Other Federal 
			 | 
			
				 
				 
			 | 
			
				 
				 
			 | 
			
				$0 
			 | 
		
		
			
				Transportation Development Credit 
			 | 
			
				 
				 
			 | 
			
				 
				 
			 | 
			
				$0 
			 | 
		
		
			
				Adjustment 
			 | 
			
				 
				 
			 | 
			
				 
				 
			 | 
			
				$0 
			 | 
		
	
	
		
			
				Total Eligible Cost 
			 | 
			
				$164,224,755 
			 | 
		
	
Part
3: Milestone Progress Report Information
	
	
	
	
	
	
	
	
		
			
				Milestone
				Progress Report Details 
			 | 
		
		
			
				Report Type 
			 | 
			
				Report Period 
			 | 
			
				Final Report? 
			 | 
			
				Report Period Begin Date 
			 | 
			
				Report Period End Date 
			 | 
			
				Report Due Date 
			 | 
			
				Submission Date 
			 | 
		
	
	
		
			
				Quarterly 
			 | 
			
				Quarter 3 (Apr - Jun), FY 2019 
			 | 
			
				No 
			 | 
			
				4/1/2019 
			 | 
			
				6/30/2019 
			 | 
			
				7/30/2019 
			 | 
			
				7/30/2019 
			 | 
		
	
	
	
	
	
	
		
			
				Status
				Log 
			 | 
		
		
			
				Previous Status 
			 | 
			
				New Status 
			 | 
			
				Updated Date 
			 | 
			
				Updated By 
			 | 
		
	
	
		
			
				Submitted 
			 | 
			
				FTA Review Complete 
			 | 
			
				9/12/2019 
			 | 
			
				Katherine Berrillo 
			 | 
		
		
			
				Work in Progress 
			 | 
			
				Submitted 
			 | 
			
				7/30/2019 
			 | 
			
				Kirnita Hinton 
			 | 
		
		
			
				Task Launched 
			 | 
			
				Work in Progress 
			 | 
			
				7/1/2019 
			 | 
			
				N/A 
			 | 
		
	
Milestone
Progress Overview Remarks 
	
	
	
		
			Remark By 
		 | 
		
			Kirnita Hinton 
		 | 
	
	
		
			Remark Type 
		 | 
		
			Award Overview 
		 | 
	
	
		
			Remark Date 
			 
		 | 
		
			7/30/2019 
			 
		 | 
	
	
		
			Remark 
			 
		 | 
		
			The projects in this grant are active
			and there are no outstanding claims or change orders in excesses
			of $100,000. 
		 | 
	
Milestone
Progress FTA Review Remarks 
	
	
	
		
			Remark By 
		 | 
		
			Katherine Berrillo 
		 | 
	
	
		
			Remark Type 
		 | 
		
			FTA Remarks 
		 | 
	
	
		
			Remark Date 
			 
		 | 
		
			9/12/2019 
			 
		 | 
	
	
		
			Remark 
			 
		 | 
		
			No Comment Entered 
		 | 
	
Milestone
Details 
	
	
		
			
				Budget Activity Line Item: 12.26.20
				- LEASE MISC RAIL EQUIPMENT 
			 | 
		
	
	
		
			
				Line Item Description:
				This Activity Line Item partially funds capital asset trackage
				agreement payments (the capital portion of the Amtrak-SEPTA rail
				trackage agreement) to Amtrak for the period of 7/1/2018 to
				06/30/2019. The total amount of the FY 2019 Amtrak payment is
				$49,608,300 ($39,686,640 Federal). To date, the FTA has provided
				$773,735 towards the costs of the FY 2019 Amtrak payment. Please
				see the Project Funding Summary attached to this grant under
				Application Documents. This project is included in the FY
				2019-2022 PA STIP under MPMS #59966 and is attached to this grant
				under Application Documents. 
				 
			 | 
		
		
			
				
					
					
					
					
					
					
						
							Line Item # 
						 | 
						
							Scope Name / Code 
						 | 
						
							Custom Item Name 
						 | 
						
							Activity 
						 | 
						
							Quantity 
						 | 
					 
					
						
							12.26.20 
						 | 
						
							RAIL TRANSITWAY LINES (122-00) 
						 | 
						
							LEASE MISC RAIL EQUIPMENT 
						 | 
						
							LEASE 
						 | 
						
							1 
						 | 
					 
				 
				 
				 
			 | 
		
		
			
				
					
					
					
					
					
						
							
								Funding Source 
							 | 
							
								Section of Statute 
							 | 
							
								CFDA Number 
							 | 
							
								Amount 
							 | 
						 
					
					
						
							
								5337 - State of Good Repair Grants 
							 | 
							
								5337 
							 | 
							
								20525 
							 | 
							
								$33,524,204 
							 | 
						 
						
							
								Local 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$270,289 
							 | 
						 
						
							
								Local/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								State 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$8,110,762 
							 | 
						 
						
							
								State/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Other Federal 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Transportation Development Credit 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Adjustment 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
					
					
						
							
								Total Eligible Cost 
							 | 
							
								$41,905,255 
							 | 
						 
					
				 
				 
				 
			 | 
		
		
			
				
					
					
						
							Milestone Name:
							Initial Expenditure 
						 | 
					 
					
						
							Milestone Description:
							Initial Expenditure 
						 | 
					 
					
						
							
								
								
								
								
								
								
									
										Revision# 
									 | 
									
										Original Estimated Completion
										Date 
									 | 
									
										Revised Completion Date 
									 | 
									
										Actual Completion Date 
									 | 
									
										Milestone Progress Remarks 
									 | 
								 
								
									
										1 
									 | 
									
										7/1/2018 
									 | 
									
										 
										 
									 | 
									
										7/1/2018 
									 | 
									
										The FY 2019 Amtrak lease payment
										began in July 2018. 
									 | 
								 
							 
							
							 
							 
						 | 
					 
				 
				 
				 
			 | 
		
	
	
	
		
			
				
				
					
						Milestone Name:
						Final Expenditure 
					 | 
				 
				
					
						Milestone Description:
						Final Expenditure 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									6/30/2019 
								 | 
								
									 
									 
								 | 
								
									6/30/2019 
								 | 
								
									The FY 2019 Amtrak Lease was
									completed In June 2019. 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				
				
					
						Milestone Name:
						Project Closeout 
					 | 
				 
				
					
						Milestone Description:
						Project Closeout 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									12/31/2019 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				Budget Activity Line Item: 12.72.09
				- FORCE ACCT VEHICLE REHAB 
			 | 
		
	
	
		
			
				Line Item Description:
				This Activity Line Item funds SEPTA's FY 2019 Rail Vehicle
				Overhaul Program (VOH). The total cost of the FY 2019 Rail
				Vehicle Overhaul Program is $47,052,881 ($37,642,305 Federal). To
				date, the FTA has provided $19,543,157 towards the costs of the
				FY 2019 Rail Vehicle Overhaul Program. This ALI fully funds the
				FY 2019 Rail Vehicle Overhaul Program (VOH). Please see the
				Project Funding Summary attached to this grant under Application
				Documents. The SEPTA Force Account Plan for the FY 2019 Vehicle
				Overhaul Program was approved by FTA on 06/25/2018 (see letter
				attached to this grant under Application Documents). The Force
				Account Plan details the overhaul type by vehicle and quantity.
				Indirect Costs will be applied to this Activity Line Item. This
				project is included in the FY 2019-2022 PA STIP under MPMS #60582
				and is attached to this grant under Application Documents. 
				 
			 | 
		
		
			
				
					
					
					
					
					
					
						
							Line Item # 
						 | 
						
							Scope Name / Code 
						 | 
						
							Custom Item Name 
						 | 
						
							Activity 
						 | 
						
							Quantity 
						 | 
					 
					
						
							12.72.09 
						 | 
						
							OTHER CAPITAL ITEMS (RAIL) (127-00) 
						 | 
						
							FY 2019 Rail VOH 
						 | 
						
							FORCE ACCOUNT 
						 | 
						
							1 
						 | 
					 
				 
				 
				 
			 | 
		
		
			
				
					
					
					
					
					
						
							
								Funding Source 
							 | 
							
								Section of Statute 
							 | 
							
								CFDA Number 
							 | 
							
								Amount 
							 | 
						 
					
					
						
							
								5337 - State of Good Repair Grants 
							 | 
							
								5337 
							 | 
							
								20525 
							 | 
							
								$18,099,148 
							 | 
						 
						
							
								Local 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$145,924 
							 | 
						 
						
							
								Local/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								State 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$4,378,863 
							 | 
						 
						
							
								State/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Other Federal 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Transportation Development Credit 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Adjustment 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
					
					
						
							
								Total Eligible Cost 
							 | 
							
								$22,623,935 
							 | 
						 
					
				 
				 
				 
			 | 
		
		
			
				
					
					
						
							Milestone Name:
							Initial Expenditure 
						 | 
					 
					
						
							Milestone Description:
							Initial Expenditure 
						 | 
					 
					
						
							
								
								
								
								
								
								
									
										Revision# 
									 | 
									
										Original Estimated Completion
										Date 
									 | 
									
										Revised Completion Date 
									 | 
									
										Actual Completion Date 
									 | 
									
										Milestone Progress Remarks 
									 | 
								 
								
									
										1 
									 | 
									
										7/1/2018 
									 | 
									
										 
										 
									 | 
									
										7/1/2018 
									 | 
									
										The FY 2019 VOH program began in
										July 2018. 
									 | 
								 
							 
							
							 
							 
						 | 
					 
				 
				 
				 
			 | 
		
	
	
	
		
			
				
				
					
						Milestone Name:
						Project Closeout 
					 | 
				 
				
					
						Milestone Description:
						Project Closeout 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									9/30/2019 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				
				
					
						Milestone Name:
						Final Expenditure 
					 | 
				 
				
					
						Milestone Description:
						Final Expenditure 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									6/30/2019 
								 | 
								
									 
									 
								 | 
								
									6/30/2019 
								 | 
								
									The FY 2018 VOH program was
									complete in June 2019. 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				Budget Activity Line Item: 12.71.11
				- OTHER - 3RD PARTY 
			 | 
		
	
	
		
			
				Line Item Description:
				This Activity Line Item funds the ninth debt service payment
				associated with a bond issuance funding for the Wayne Junction
				Intermodal Facility Reconstruction Project. The total cost of the
				project is approximately $29,391,186. To date, FTA has provided
				$19,477,214. Please see Project Funding Summary attached to this
				grant under Application Documents. This project is included in
				the FY 2019-2022 PA STIP under MPMS #60275 and is attached to
				this grant under Application Documents. 
				 
			 | 
		
		
			
				
					
					
					
					
					
					
						
							Line Item # 
						 | 
						
							Scope Name / Code 
						 | 
						
							Custom Item Name 
						 | 
						
							Activity 
						 | 
						
							Quantity 
						 | 
					 
					
						
							12.71.11 
						 | 
						
							OTHER CAPITAL ITEMS (RAIL) (127-00) 
						 | 
						
							OTHER - 3RD PARTY 
						 | 
						
							3RD PARTY CONSULTANT SERVICES (RAIL) 
						 | 
						
							0 
						 | 
					 
				 
				 
				 
			 | 
		
		
			
				
					
					
					
					
					
						
							
								Funding Source 
							 | 
							
								Section of Statute 
							 | 
							
								CFDA Number 
							 | 
							
								Amount 
							 | 
						 
					
					
						
							
								5337 - State of Good Repair Grants 
							 | 
							
								5337 
							 | 
							
								20525 
							 | 
							
								$1,326,194 
							 | 
						 
						
							
								Local 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$10,693 
							 | 
						 
						
							
								Local/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								State 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$320,856 
							 | 
						 
						
							
								State/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Other Federal 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Transportation Development Credit 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Adjustment 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
					
					
						
							
								Total Eligible Cost 
							 | 
							
								$1,657,743 
							 | 
						 
					
				 
				 
				 
			 | 
		
		
			
				
					
					
						
							Milestone Name:
							Initial Expenditure 
						 | 
					 
					
						
							Milestone Description:
							Initial Expenditure 
						 | 
					 
					
						
							
								
								
								
								
								
								
									
										Revision# 
									 | 
									
										Original Estimated Completion
										Date 
									 | 
									
										Revised Completion Date 
									 | 
									
										Actual Completion Date 
									 | 
									
										Milestone Progress Remarks 
									 | 
								 
								
									
										1 
									 | 
									
										6/1/2019 
									 | 
									
										 
										 
									 | 
									
										6/1/2019 
									 | 
									
										The FY 2020 Debt Service payment
										was due in June 2019 or as soon as this grant was awarded. 
									 | 
								 
							 
							
							 
							 
						 | 
					 
				 
				 
				 
			 | 
		
	
	
	
		
			
				
				
					
						Milestone Name:
						Project Closeout 
					 | 
				 
				
					
						Milestone Description:
						Project Closeout 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									12/31/2019 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				
				
					
						Milestone Name:
						Final Expenditure 
					 | 
				 
				
					
						Milestone Description:
						Final Expenditure 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									6/30/2019 
								 | 
								
									 
									 
								 | 
								
									6/30/2019 
								 | 
								
									The FY 2020 Debt Service payment
									was made in June 2019. 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				Budget Activity Line Item: 12.71.11
				- OTHER - 3RD PARTY 
			 | 
		
	
	
		
			
				Line Item Description:
				This Activity Line Item funds the ninth debt service payment
				associated with a bond issuance for the Silverliner V Regional
				Rail Car Acquisition. The total cost of the Regional Rail Car
				Acquisition is approximately $319.7 million. To date, FTA has
				provided $202,668,001. Please see Project Funding Summary
				attached to this grant under Application Documents. This project
				is included in the FY 2019-2022 PA STIP under MPMS #60275 and is
				attached to this grant under Application Documents. 
				 
			 | 
		
		
			
				
					
					
					
					
					
					
						
							Line Item # 
						 | 
						
							Scope Name / Code 
						 | 
						
							Custom Item Name 
						 | 
						
							Activity 
						 | 
						
							Quantity 
						 | 
					 
					
						
							12.71.11 
						 | 
						
							OTHER CAPITAL ITEMS (RAIL) (127-00) 
						 | 
						
							OTHER - 3RD PARTY 
						 | 
						
							3RD PARTY CONSULTANT SERVICES (RAIL) 
						 | 
						
							1 
						 | 
					 
				 
				 
				 
			 | 
		
		
			
				
					
					
					
					
					
						
							
								Funding Source 
							 | 
							
								Section of Statute 
							 | 
							
								CFDA Number 
							 | 
							
								Amount 
							 | 
						 
					
					
						
							
								5337 - State of Good Repair Grants 
							 | 
							
								5337 
							 | 
							
								20525 
							 | 
							
								$11,929,405 
							 | 
						 
						
							
								Local 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$96,181 
							 | 
						 
						
							
								Local/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								State 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$2,886,171 
							 | 
						 
						
							
								State/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Other Federal 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Transportation Development Credit 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Adjustment 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
					
					
						
							
								Total Eligible Cost 
							 | 
							
								$14,911,757 
							 | 
						 
					
				 
				 
				 
			 | 
		
		
			
				
					
					
						
							Milestone Name:
							Initial Expenditure 
						 | 
					 
					
						
							Milestone Description:
							Initial Expenditure 
						 | 
					 
					
						
							
								
								
								
								
								
								
									
										Revision# 
									 | 
									
										Original Estimated Completion
										Date 
									 | 
									
										Revised Completion Date 
									 | 
									
										Actual Completion Date 
									 | 
									
										Milestone Progress Remarks 
									 | 
								 
								
									
										1 
									 | 
									
										6/1/2019 
									 | 
									
										 
										 
									 | 
									
										6/1/2019 
									 | 
									
										The FY 2020 Debt Service payment
										was due in June 2019 or as soon as this grant was awarded. 
									 | 
								 
							 
							
							 
							 
						 | 
					 
				 
				 
				 
			 | 
		
	
	
	
		
			
				
				
					
						Milestone Name:
						Project Closeout 
					 | 
				 
				
					
						Milestone Description:
						Project Closeout 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									12/31/2019 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				
				
					
						Milestone Name:
						Final Expenditure 
					 | 
				 
				
					
						Milestone Description:
						Final Expenditure 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									6/30/2019 
								 | 
								
									 
									 
								 | 
								
									6/30/2019 
								 | 
								
									The FY 2020 Debt Service payment
									was made in June 2019. 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				Budget Activity Line Item: 12.7A.00
				- PREVENTIVE MAINTENANCE (RAIL) 
			 | 
		
	
	
		
			
				Line Item Description:
				This Activity Line Item funds Preventive Maintenance for all
				eligible activities associated with vehicle and facility
				maintenance, including: 1) repair of buildings, grounds, and
				equipment; 2) operation of electric power facilities; 3)
				maintenance of vehicle movement control systems, fare collection,
				counting equipment and structures; and 4) maintenance of general
				administration buildings, grounds, equipment, and electrical
				facilities, as defined in the National Transit Database Reporting
				Manual for the period of 7/1/2018 to 6/30/2019. This project is
				included in the FY 2019-2022 PA STIP under MPMS #60317 and is
				attached to this grant under Application Documents. 
				 
			 | 
		
		
			
				
					
					
					
					
					
					
						
							Line Item # 
						 | 
						
							Scope Name / Code 
						 | 
						
							Custom Item Name 
						 | 
						
							Activity 
						 | 
						
							Quantity 
						 | 
					 
					
						
							12.7A.00 
						 | 
						
							OTHER CAPITAL ITEMS (RAIL) (127-00) 
						 | 
						
							PREVENTIVE MAINTENANCE (RAIL) 
						 | 
						
							OTHER CAPITAL ITEMS (RAIL) 
						 | 
						
							1 
						 | 
					 
				 
				 
				 
			 | 
		
		
			
				
					
					
					
					
					
						
							
								Funding Source 
							 | 
							
								Section of Statute 
							 | 
							
								CFDA Number 
							 | 
							
								Amount 
							 | 
						 
					
					
						
							
								5337 - State of Good Repair Grants 
							 | 
							
								5337 
							 | 
							
								20525 
							 | 
							
								$36,200,000 
							 | 
						 
						
							
								Local 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$9,050,000 
							 | 
						 
						
							
								Local/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								State 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								State/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Other Federal 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Transportation Development Credit 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Adjustment 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
					
					
						
							
								Total Eligible Cost 
							 | 
							
								$45,250,000 
							 | 
						 
					
				 
				 
				 
			 | 
		
		
			
				
					
					
						
							Milestone Name:
							Initial Expenditure 
						 | 
					 
					
						
							Milestone Description:
							Initial Expenditure 
						 | 
					 
					
						
							
								
								
								
								
								
								
									
										Revision# 
									 | 
									
										Original Estimated Completion
										Date 
									 | 
									
										Revised Completion Date 
									 | 
									
										Actual Completion Date 
									 | 
									
										Milestone Progress Remarks 
									 | 
								 
								
									
										1 
									 | 
									
										7/1/2018 
									 | 
									
										 
										 
									 | 
									
										7/1/2018 
									 | 
									
										The FY 2019 Preventive
										Maintenance Program began on 7/1/218. 
									 | 
								 
							 
							
							 
							 
						 | 
					 
				 
				 
				 
			 | 
		
	
	
	
		
			
				
				
					
						Milestone Name:
						Final Expenditure 
					 | 
				 
				
					
						Milestone Description:
						Final Expenditure 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									6/30/2019 
								 | 
								
									 
									 
								 | 
								
									6/30/2019 
								 | 
								
									The FY 2019 Preventive Maintenance
									program was completed in June 2019. 
									 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				
				
					
						Milestone Name:
						Project Closeout 
					 | 
				 
				
					
						Milestone Description:
						Project Closeout 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									12/30/2019 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				Budget Activity Line Item: 12.34.02
				- REHAB/RENOV - RAIL STATION 
			 | 
		
	
	
		
			
				Line Item Description:
				This Activity Line Item funds Phase 1 of the Exton Station
				Improvements project. Phase 1 includes the construction of high
				level platforms with canopies and wind screens; stormwater
				management improvements; a new station building; fully ADA
				compliant facilities; and new lighting, signage, security
				features, and passenger amenities. The total project cost for the
				Exton Station Improvements Project is $24,420,158 ($17,316,530
				Federal). To date, FTA has provided $17,316,530; this line item
				increment fully funds this project. Please see the Project
				Funding Summary attached to this grant under Application
				Documents. Indirect costs will be applied to this Activity Line
				Item. The useful life for this facility is 40 years as per FTA
				Circular 5010.1E. This project is included in the FY 2019-2022 PA
				STIP under MPMS #93588 and is attached to this grant under
				Application Documents. 
				 
			 | 
		
		
			
				
					
					
					
					
					
					
						
							Line Item # 
						 | 
						
							Scope Name / Code 
						 | 
						
							Custom Item Name 
						 | 
						
							Activity 
						 | 
						
							Quantity 
						 | 
					 
					
						
							12.34.02 
						 | 
						
							RAIL - STATION/STOPS/TERMINALS
							(123-00) 
						 | 
						
							REHAB/RENOV - RAIL STATION 
						 | 
						
							REHAB/RENOVATE 
						 | 
						
							1 
						 | 
					 
				 
				 
				 
			 | 
		
		
			
				
					
					
					
					
					
						
							
								Funding Source 
							 | 
							
								Section of Statute 
							 | 
							
								CFDA Number 
							 | 
							
								Amount 
							 | 
						 
					
					
						
							
								5337 - State of Good Repair Grants 
							 | 
							
								5337 
							 | 
							
								20525 
							 | 
							
								$6,000,000 
							 | 
						 
						
							
								Local 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$48,375 
							 | 
						 
						
							
								Local/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								State 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$1,451,625 
							 | 
						 
						
							
								State/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Other Federal 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Transportation Development Credit 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Adjustment 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
					
					
						
							
								Total Eligible Cost 
							 | 
							
								$7,500,000 
							 | 
						 
					
				 
				 
				 
			 | 
		
		
			
				
					
					
						
							Milestone Name:
							RFP/IFB 
						 | 
					 
					
						
							Milestone Description:
							RFP/IFB 
						 | 
					 
					
						
							
								
								
								
								
								
								
									
										Revision# 
									 | 
									
										Original Estimated Completion
										Date 
									 | 
									
										Revised Completion Date 
									 | 
									
										Actual Completion Date 
									 | 
									
										Milestone Progress Remarks 
									 | 
								 
								
									
										1 
									 | 
									
										4/15/2015 
									 | 
									
										 
										 
									 | 
									
										4/15/2015 
									 | 
									
										SEPTA advertised this project in
										April 2015. 
									 | 
								 
							 
							
							 
							 
						 | 
					 
				 
				 
				 
			 | 
		
	
	
	
		
			
				
				
					
						Milestone Name:
						Contract Award 
					 | 
				 
				
					
						Milestone Description:
						Contract Award 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									6/30/2015 
								 | 
								
									 
									 
								 | 
								
									6/30/2015 
								 | 
								
									SEPTA awarded the contract in June
									2015. 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				
				
					
						Milestone Name:
						NTP 
					 | 
				 
				
					
						Milestone Description:
						NTP 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									6/30/2015 
								 | 
								
									 
									 
								 | 
								
									6/30/2015 
								 | 
								
									SEPTA issued a notice to proceed
									June 2015. 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				Budget Activity Line Item: 12.63.01
				- CONSTRUCT TRAIN CONTROL-SIGNAL SYS 
			 | 
		
	
	
		
			
				Line Item Description:
				This Activity Line Item funds SEPTA's Positive Train Control
				(PTC) project. The total project cost for the Positive Train
				Control project is $170,000,000. To date, FTA has provided
				$122,183,999. Please see Project Funding Summary attached to this
				grant under Application Documents. This project is included in
				the FY 2019-2022 PA STIP under MPMS# 60255 and is attached to
				this grant under Application Documents. 
				 
			 | 
		
		
			
				
					
					
					
					
					
					
						
							Line Item # 
						 | 
						
							Scope Name / Code 
						 | 
						
							Custom Item Name 
						 | 
						
							Activity 
						 | 
						
							Quantity 
						 | 
					 
					
						
							12.63.01 
						 | 
						
							SIGNAL/COMMUNICATION (RAIL) (126-00) 
						 | 
						
							CONSTRUCT TRAIN CONTROL-SIGNAL SYS 
						 | 
						
							CONSTRUCTION 
						 | 
						
							1 
						 | 
					 
				 
				 
				 
			 | 
		
		
			
				
					
					
					
					
					
						
							
								Funding Source 
							 | 
							
								Section of Statute 
							 | 
							
								CFDA Number 
							 | 
							
								Amount 
							 | 
						 
					
					
						
							
								5337 - State of Good Repair Grants 
							 | 
							
								5337 
							 | 
							
								20525 
							 | 
							
								$4,000,000 
							 | 
						 
						
							
								Local 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$32,250 
							 | 
						 
						
							
								Local/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								State 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$967,750 
							 | 
						 
						
							
								State/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Other Federal 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Transportation Development Credit 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Adjustment 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
					
					
						
							
								Total Eligible Cost 
							 | 
							
								$5,000,000 
							 | 
						 
					
				 
				 
				 
			 | 
		
		
			
				
					
					
						
							Milestone Name:
							RFP/IFB 
						 | 
					 
					
						
							Milestone Description:
							RFP/IFB 
						 | 
					 
					
						
							
								
								
								
								
								
								
									
										Revision# 
									 | 
									
										Original Estimated Completion
										Date 
									 | 
									
										Revised Completion Date 
									 | 
									
										Actual Completion Date 
									 | 
									
										Milestone Progress Remarks 
									 | 
								 
								
									
										1 
									 | 
									
										11/1/2010 
									 | 
									
										 
										 
									 | 
									
										11/1/2010 
									 | 
									
										SEPTA advertised this project in
										January. 
									 | 
								 
							 
							
							 
							 
						 | 
					 
				 
				 
				 
			 | 
		
	
	
	
		
			
				
				
					
						Milestone Name:
						Contract Award 
					 | 
				 
				
					
						Milestone Description:
						Contract Award 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									3/30/2012 
								 | 
								
									 
									 
								 | 
								
									3/29/2012 
								 | 
								
									SEPTA issued a noticed to proceed
									for this project in March 2012. 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				
				
					
						Milestone Name:
						Contract Complete 
					 | 
				 
				
					
						Milestone Description:
						Contract Complete 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									12/31/2020 
								 | 
								
									12/30/2020 
								 | 
								
									 
									 
								 | 
								
									SEPTA currently anticipates the
									contract will be complete in 2020. SEPTA previously extended
									the scope and duration of the PTC contract to address
									additional passenger safety measures that were previously
									not feasible for technical, financial and/or service related
									reasons. 
									 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				
				
					
						Milestone Name:
						Project Closeout 
					 | 
				 
				
					
						Milestone Description:
						Project Closeout 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									6/1/2021 
								 | 
								
									6/1/2021 
								 | 
								
									 
									 
								 | 
								
									SEPTA currently anticipates the
									project will be closed out in June 2021. 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				Budget Activity Line Item: 12.34.02
				- REHAB/RENOV - RAIL STATION 
			 | 
		
	
	
		
			
				Line Item Description:
				This Activity Line Item funds Phase 1 of the Exton Station
				Improvements project. Phase 1 includes the construction of high
				level platforms with canopies and wind screens; stormwater
				management improvements; a new station building; fully ADA
				compliant facilities; and new lighting, signage, security
				features, and passenger amenities. The total project cost for the
				Exton Station Improvements Project is $24,420,158 ($17,316,530
				Federal). To date, FTA has provided $17,316,530; this line item
				increment fully funds this project. Please see the Project
				Funding Summary attached to this grant under Application
				Documents. Indirect costs will be applied to this Activity Line
				Item. The useful life for this facility is 40 years as per FTA
				Circular 5010.1E. This project is included in the FY 2019-2022 PA
				STIP under MPMS #93588 and is attached to this grant under
				Application Documents. 
				 
			 | 
		
		
			
				
					
					
					
					
					
					
						
							Line Item # 
						 | 
						
							Scope Name / Code 
						 | 
						
							Custom Item Name 
						 | 
						
							Activity 
						 | 
						
							Quantity 
						 | 
					 
					
						
							12.34.02 
						 | 
						
							RAIL - STATION/STOPS/TERMINALS
							(123-00) 
						 | 
						
							REHAB/RENOV - RAIL STATION 
						 | 
						
							REHAB/RENOVATE 
						 | 
						
							1 
						 | 
					 
				 
				 
				 
			 | 
		
		
			
				
					
					
					
					
					
						
							
								Funding Source 
							 | 
							
								Section of Statute 
							 | 
							
								CFDA Number 
							 | 
							
								Amount 
							 | 
						 
					
					
						
							
								5337 - State of Good Repair Grants 
							 | 
							
								5337 
							 | 
							
								20525 
							 | 
							
								$6,000,000 
							 | 
						 
						
							
								Local 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$48,375 
							 | 
						 
						
							
								Local/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								State 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$1,451,625 
							 | 
						 
						
							
								State/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Other Federal 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Transportation Development Credit 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Adjustment 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
					
					
						
							
								Total Eligible Cost 
							 | 
							
								$7,500,000 
							 | 
						 
					
				 
				 
				 
			 | 
		
		
			
				
					
					
						
							Milestone Name:
							Contract Complete 
						 | 
					 
					
						
							Milestone Description:
							Contract Complete 
						 | 
					 
					
						
							
								
								
								
								
								
								
									
										Revision# 
									 | 
									
										Original Estimated Completion
										Date 
									 | 
									
										Revised Completion Date 
									 | 
									
										Actual Completion Date 
									 | 
									
										Milestone Progress Remarks 
									 | 
								 
								
									
										1 
									 | 
									
										9/30/2019 
									 | 
									
										9/30/2019 
									 | 
									
										 
										 
									 | 
									
										SEPTA currently anticipates that
										the contract will be complete. Construction 92% complete. 
									 | 
								 
							 
							
							 
							 
						 | 
					 
				 
				 
				 
			 | 
		
	
	
	
		
			
				
				
					
						Milestone Name:
						Project Closeout 
					 | 
				 
				
					
						Milestone Description:
						Project Closeout 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									12/31/2019 
								 | 
								
									1/30/2020 
								 | 
								
									 
									 
								 | 
								
									SEPTA anticipates that the project
									will be closed out in January 2020. 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				Budget Activity Line Item: 12.63.01
				- CONSTRUCT TRAIN CONTROL-SIGNAL SYS 
			 | 
		
	
	
		
			
				Line Item Description:
				This Activity Line Item funds SEPTA's Positive Train Control
				(PTC) project. The total project cost for the Positive Train
				Control project is $170,000,000. To date, FTA has provided
				$122,183,999. Please see Project Funding Summary attached to this
				grant under Application Documents. This project is included in
				the FY 2019-2022 PA STIP under MPMS# 60255 and is attached to
				this grant under Application Documents. 
				 
			 | 
		
		
			
				
					
					
					
					
					
					
						
							Line Item # 
						 | 
						
							Scope Name / Code 
						 | 
						
							Custom Item Name 
						 | 
						
							Activity 
						 | 
						
							Quantity 
						 | 
					 
					
						
							12.63.01 
						 | 
						
							SIGNAL/COMMUNICATION (RAIL) (126-00) 
						 | 
						
							CONSTRUCT TRAIN CONTROL-SIGNAL SYS 
						 | 
						
							CONSTRUCTION 
						 | 
						
							1 
						 | 
					 
				 
				 
				 
			 | 
		
		
			
				
					
					
					
					
					
						
							
								Funding Source 
							 | 
							
								Section of Statute 
							 | 
							
								CFDA Number 
							 | 
							
								Amount 
							 | 
						 
					
					
						
							
								5337 - State of Good Repair Grants 
							 | 
							
								5337 
							 | 
							
								20525 
							 | 
							
								$4,000,000 
							 | 
						 
						
							
								Local 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$32,250 
							 | 
						 
						
							
								Local/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								State 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$967,750 
							 | 
						 
						
							
								State/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Other Federal 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Transportation Development Credit 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Adjustment 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
					
					
						
							
								Total Eligible Cost 
							 | 
							
								$5,000,000 
							 | 
						 
					
				 
				 
				 
			 | 
		
		
			
				
					
					
						
							Milestone Name:
							NTP 
						 | 
					 
					
						
							Milestone Description:
							NTP 
						 | 
					 
					
						
							
								
								
								
								
								
								
									
										Revision# 
									 | 
									
										Original Estimated Completion
										Date 
									 | 
									
										Revised Completion Date 
									 | 
									
										Actual Completion Date 
									 | 
									
										Milestone Progress Remarks 
									 | 
								 
								
									
										1 
									 | 
									
										12/30/2012 
									 | 
									
										 
										 
									 | 
									
										3/29/2012 
									 | 
									
										SEPTA issued a notice to proceed
										for this contract in March 2012. 
									 | 
								 
							 
							
							 
							 
						 | 
					 
				 
				 
				 
			 | 
		
	
	
	
		
			
				Budget Activity Line Item: 12.72.09
				- FORCE ACCT VEHICLE REHAB 
			 | 
		
	
	
		
			
				Line Item Description:
				This Activity Line Item funds SEPTA's FY 2020 Rail Vehicle
				Overhaul Program (VOH). The total cost of the FY 2020 Rail
				Vehicle Overhaul Program is $49,521,153 ($39,616,922 Federal).
				This ALI is the first increment of funding for the FY 2020 Rail
				VOH Program. Please see the Project Funding Summary attached to
				this grant under Application Documents. The SEPTA Force Account
				Plan for the FY 2020 Vehicle Overhaul Program is presently under
				development by SEPTA. Prior to incurring any costs for the FY
				2020 Vehicle Overhaul Program, SEPTA will ensure that the Force
				Account Plan for the FY 2020 VOH is approved. The Force Account
				Plan details the overhaul type by vehicle and quantity. Indirect
				Costs will be applied to this Activity Line Item. This project is
				included in the FY 2019-2022 PA STIP under MPMS #60582 and is
				attached to this grant under Application Documents. 
				 
			 | 
		
		
			
				
					
					
					
					
					
					
						
							Line Item # 
						 | 
						
							Scope Name / Code 
						 | 
						
							Custom Item Name 
						 | 
						
							Activity 
						 | 
						
							Quantity 
						 | 
					 
					
						
							12.72.09 
						 | 
						
							OTHER CAPITAL ITEMS (RAIL) (127-00) 
						 | 
						
							FY 2020 Rail VOH 
						 | 
						
							FORCE ACCOUNT 
						 | 
						
							1 
						 | 
					 
				 
				 
				 
			 | 
		
		
			
				
					
					
					
					
					
						
							
								Funding Source 
							 | 
							
								Section of Statute 
							 | 
							
								CFDA Number 
							 | 
							
								Amount 
							 | 
						 
					
					
						
							
								5337 - State of Good Repair Grants 
							 | 
							
								5337 
							 | 
							
								20525 
							 | 
							
								$20,300,852 
							 | 
						 
						
							
								Local 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$163,676 
							 | 
						 
						
							
								Local/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								State 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$4,911,537 
							 | 
						 
						
							
								State/In-Kind 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Other Federal 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Transportation Development Credit 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
						
							
								Adjustment 
							 | 
							
								 
								 
							 | 
							
								 
								 
							 | 
							
								$0 
							 | 
						 
					
					
						
							
								Total Eligible Cost 
							 | 
							
								$25,376,065 
							 | 
						 
					
				 
				 
				 
			 | 
		
		
			
				
					
					
						
							Milestone Name:
							Initial Expenditure 
						 | 
					 
					
						
							Milestone Description:
							Initial Expenditure 
						 | 
					 
					
						
							
								
								
								
								
								
								
									
										Revision# 
									 | 
									
										Original Estimated Completion
										Date 
									 | 
									
										Revised Completion Date 
									 | 
									
										Actual Completion Date 
									 | 
									
										Milestone Progress Remarks 
									 | 
								 
								
									
										1 
									 | 
									
										7/1/2019 
									 | 
									
										 
										 
									 | 
									
										 
										 
									 | 
									
										 
										 
									 | 
								 
							 
							
							 
							 
						 | 
					 
				 
				 
				 
			 | 
		
	
	
	
		
			
				
				
					
						Milestone Name:
						Final Expenditure 
					 | 
				 
				
					
						Milestone Description:
						Final Expenditure 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									6/30/2020 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
	
	
		
			
				
				
					
						Milestone Name:
						Project Closeout 
					 | 
				 
				
					
						Milestone Description:
						Project Closeout 
					 | 
				 
				
					
						
							
							
							
							
							
							
								
									Revision# 
								 | 
								
									Original Estimated Completion
									Date 
								 | 
								
									Revised Completion Date 
								 | 
								
									Actual Completion Date 
								 | 
								
									Milestone Progress Remarks 
								 | 
							 
							
								
									1 
								 | 
								
									9/30/2020 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
								
									 
									 
								 | 
							 
						 
						
						 
						 
					 | 
				 
			 
			 
			 
		 | 
	
| File Type | application/vnd.openxmlformats-officedocument.wordprocessingml.document | 
| File Title | View Print Milestone Progress Report | 
| Author | Hu, Eric (FTA) | 
| File Modified | 0000-00-00 | 
| File Created | 2023-08-27 |