| 
				Federal-Aid
				Policy GuideJuly 6, 2005, Transmittal
				34
 
				NS
				23 CFR 646B 
				Attachment
				3 Non-Regulatory
				SupplementAttachment
				OPI:
				HSA-10 USE
				OF FIXED AMOUNT (LUMP SUM) PAYMENTS TO RAILROADS (PARAGRAPH 6, NS
				23 CFR 646B) 
				 Occasionally
				on Federal-aid highway projects the States consider proposals
				that involve the use of fixed amount (lump sum) payments to
				railroads either as reimbursement for needed adjustments to
				accommodate construction of the highway project or as
				compensation for facilities taken. The
				FHWA regulations have long treated railroad facilities impacted
				by highway construction as essential public services that must be
				maintained if the need for the services continues to exist. Where
				services must be maintained, the FHWA may reimburse the State
				based upon necessary costs to restore the essential services in
				the most economical method. This is usually done by paying for
				construction of a replacement facility. Where the railroad and
				the highway agencies agree that existing facilities do not need
				to be replaced, the FHWA should pay for the railroad facilities
				as a right-of-way acquisition matter. The FHWA policy and use of
				fixed amount (lump sum) payments are discussed below. Case
				I - Operational Capabilities are to be Functionally Restored 
				 The
				FHWA's regulations covering reimbursement for railroad work on
				Federal-aid highway projects are contained in 23 CFR 140, Subpart
				I. The basic concept incorporated into these regulations is that
				FHWA is willing to reimburse actual costs incurred to
				functionally restore a railroad’s existing operating
				facilities which existed prior to undertaking a highway project.
				It is intended that a railroad's financial and productive
				situation be maintained as if the adjustment needed for the
				highway project had not occurred. This does not mean that a
				replica facility is required, rather that the railroad is to be
				made whole by restoring the existing functions of the impacted
				facilities. Typically,
				a railroad uses its own forces or lets a contract to accomplish
				the needed adjustments to its facilities. Records of actual costs
				incurred then form the basis for FHWA reimbursement to the State.
				For work performed by a railroad with its own forces, FHWA
				regulations allow a fixed amount final payment based on an
				estimate of costs prior to construction. This is commonly known
				as the lump sum payment method. For railroad work, FHWA's lump
				sum payment regulation is 23 CFR 646.216(d)(3). The
				lump sum payment method should only be used where the end
				product, in this case the railroad adjustment, can be clearly and
				concisely defined. The cost estimate in support of the lump sum
				agreement should be accurate, comprehensive, verifiable, and in
				sufficient detail to give a clear picture of work involved and
				the cost of the individual items. A principal benefit of using
				the lump sum payment method is that it should reduce
				administrative and record keeping costs associated with
				documenting payment for completed work. However, these savings
				may be offset by inaccuracies in the cost estimating process. In
				recognition of this, the regulation establishes a $100,000
				ceiling for use of the lump sum payment method, although for
				routine railroad crossing safety improvements (i.e., active
				warning devices, crossing surface, etc.) there is no ceiling. The
				railroad regulation contains a mechanism for approving lump sum
				amounts where this is found to be in the public interest.
				Approval of proposals to exceed the $100,000 ceiling should be a
				relatively rare occurrence. Two situations where this may be
				justified are as follows: -
				Where the estimated cost of the eligible adjustment work slightly
				exceeds, for example, by no more than a few thousand dollars, the
				$100,000 ceiling. In this case the ceiling is not being treated
				as an inviolable barrier and some flexibility is allowed. -
				Where the cost of the railroad work eligible for Federal-aid
				participation represents only a small portion of the overall cost
				for all the railroad work that is being performed in conjunction
				with the construction of the highway project. For example, a
				railroad may be undertaking a major upgrading of its facilities
				in an area where a highway project occurs, and the portion of the
				work eligible for Federal-aid participation may be relatively
				small in comparison, for example $75,000 out of an $800,000
				effort. In this case, it may make sense for the highway agency to
				agree to a fixed payment to represent its share of the overall
				work being accomplished, thus simplifying administration of the
				project. In
				either of the above situations, the lump sum payment method
				should only be used where the work can be clearly defined and the
				costs accurately estimated. Also, whenever a lump sum payment is
				used, the highway agency should still verify that the eligible
				work has been satisfactorily completed in accordance with the
				approved agreement, plans, and specifications before
				reimbursement can be approved. Processing
				of a State's proposal for a lump sum payment for railroad work in
				excess of $100,000 other than for crossing safety projects
				requires approval by the Division Administrator. Case
				II - Operational Capabilities Need not be Functionally Restored 
				 Where
				the railroad determines that its existing facilities do not need
				to be replaced to maintain its operational capabilities, then
				payment for the railroad facilities needed to accommodate
				construction of the highway project should be handled as a
				right-of-way acquisition matter. The fixed amount (lump sum)
				payment for the real property interest of the railroad to be
				acquired would be based on the fair market value of its existing
				facilities developed in accordance with approved State
				right-of-way appraisal and acquisition procedures. Any
				administrative settlement over and above the fair market value
				should be supported in accordance with 49 CFR 24.102(i). Various
				means, such as appraisals, recent court awards, estimated trial
				costs, or valuation problems are recognized as providing support
				for a settlement value. Case
				III - Payment for Nonoperational Facilities 
				 Instances
				can arise where a highway project may require the acquisition of
				a portion of a railroad’s property or facilities that are
				not directly a part of the company's physical plant providing the
				service (e.g., an office that houses the company’s
				marketing and billing operations). In these cases, the fixed
				payment to the railroad should always be based on applicable
				right-of-way procedures. |